Brighton Avenue Sewer Separation Project

PROJECT UPDATES

WE 4/2/21 Project Update:

DDI construction began to mobilize and bring materials and equipment to the site.

The first project weekly field meeting was held on site.

Utility test pits were completed on Lomond Street.

Upcoming Project Work WE 4/9/21:

The contractor will begin to install PWD water main cut in valves in Rowe Avenue (4/5/21) and Dorset Street (4/7/21) in preparation of setting up the project's temporary water system. The temporary water system is required to be able to replace the existing water mains in the project area.

The contractor will also begin to install a riprap scour protection pad in preparation for the installation of the 42" storm drain outfall pipe at the end of Meriline Avenue.



"This project was successfully bid in December of 2020 and awarded to DDI Construction at a contract price of $1,286,897.00.  
It is anticipated that the contractor will mobilize to the site the week of March 29th and begin construction work on Meriline Avenue the week of April 5th."